In short

A 75-day office project runs in three phases: days 1 to 15 for design, days 16 to 65 for the build, and days 66 to 75 for snagging and move-in. It works when decisions are made early, the price is fixed before work starts, and long-lead items are ordered as soon as the design is frozen.

  • Design takes 15 days, the build 50 days, and snagging with move-in the final 10.
  • ByzBay offers this for any office under 10,000 sq ft at a fixed price agreed before work starts, with the 75 days counted from the day both sides sign off the final design and the site is handed over.
  • Most schedule risk sits in decisions made, or not made, before the build begins.
  • Settle headcount, rooms, approvals and a single sign-off owner before day one.

Where does the speed come from?

Speed comes from sequencing, not rushing. The design is frozen at day 15, so the build starts from a final drawing and each trade works to a fixed plan instead of reacting to changes.

ByzBay designs and builds any office under 10,000 sq ft in 75 days, at a fixed price agreed before work starts. Under ByzBay’s terms, the 75 days run from the day both sides sign off the final design and the site is handed over, and extend for changes you ask for, permits and approvals outside ByzBay’s control, and force majeure. The design-and-build contract for your project sets its dates and prevails over the general terms, so check which day counts as day one. A larger office falls outside that offer, so do not assume the same programme for it.

Market conditions favour a disciplined programme. In Cushman & Wakefield’s 2026 survey of Indian fit-out contractors, 61% expected lead times to stay level over the following six months and around a third expected a slight increase.

What happens in days 1 to 15?

The first 15 days produce the drawings, the specification and the price. Every decision made now costs less than the same decision made on site.

Keep the circle small. One person on your side who can approve layout, finishes and budget saves more days than any shortcut later in the build.

Ask for drawings you can read: a furniture layout, a ceiling plan for lights and air conditioning, and a power and data plan. Signing off those three is what freezing the design means in practice.

  • Brief: headcount today and in 18 months, meeting rooms, cabins, pantry and storage.
  • Layout: seating plan, circulation and room sizes drawn against the actual floor plate.
  • Specification: finishes, lighting, power points, data points and air-conditioning requirements.
  • Fixed price: the total agreed before work starts, so the scope is clear to both sides.
  • Orders: long-lead items such as furniture and glazing placed as soon as the design is frozen.

What happens in days 16 to 65?

The build runs for 50 days in a fixed order of trades. Services such as electrical, data and air conditioning go in before ceilings and partitions close them up, and finishes come last.

A weekly site review is the simplest way to keep the plan honest. Anything that changes the drawing should be priced and agreed in writing before it is built, so the fixed price keeps its meaning.

Building rules shape the week-to-week plan. Many commercial towers limit noisy or dusty work to nights or weekends and ask for work permits before contractors start, so build those rules into the programme from the first day.

  • Strip-out, then marking out walls and rooms on the floor.
  • First fix: electrical, data, plumbing and air-conditioning routes.
  • Partitions, ceilings and glazing.
  • Second fix: lights, sockets, data points and air-conditioning outlets.
  • Flooring, joinery, paint and furniture.

What happens in days 66 to 75?

The final ten days cover snagging and move-in. Snagging means walking the space with a checklist, recording every defect and fixing it before the team arrives.

Move-in needs a plan of its own. Place the furniture, test power and connectivity at every desk, and walk the team through the space before the first working day.

Book the move for the end of the window, not the start. A team that arrives while snags are still open ends up working around tradespeople, which helps nobody.

  • Doors, locks and access control work as specified.
  • Every power and data point is live and labelled.
  • Air conditioning reaches each room and cabin.
  • Finishes are free of marks, gaps and damage.
  • Fire and safety signage is in place.

What should you decide before day one?

The faster the project, the less room there is for open questions. A short list answered up front protects the schedule.

Write the answers into a one-page brief and share it with everyone whose opinion will be asked. The brief becomes the test for every later request: if it is not in the brief, it is a change.

  • Who signs off the design, and by which date.
  • Whether the landlord or building management must approve the plan under your lease.
  • Your headcount now and the number you expect in a year.
  • Which rooms must be enclosed and which can stay open.
  • The budget ceiling, so the design is not drawn beyond it.

What usually causes delays?

Most delays start before the first wall goes up. Late design sign-off, a changing headcount and items ordered after the build has started push the programme out more than work on site does.

The cure is discipline in the first 15 days: one named decision-maker, one dated sign-off and a locked list of long-lead items. After that, price every change in writing and check whether it moves the handover date.

Keep a short risk list alongside the programme. Give each item an owner and a date by which it must be resolved, and review it at the same weekly meeting.

  • A second round of layout changes after the design freeze.
  • Furniture or glazing ordered late.
  • Landlord or building approvals sought after work has started.
  • Internet circuits ordered too late to be live on move-in day.
  • Move-in booked before snagging is complete.

Is a 75-day build right for you?

It suits teams that know their headcount, want a fixed price and need to move in on a set date. It suits you less if the brief still changes every week, because late changes stretch any schedule. Be honest about which of the two describes your team before you commit to a move date.

To talk through a plan for your floor, book a site visit on byzbay.com or message ByzBay on WhatsApp at +91 8600 351 721.

Questions

Which offices qualify for ByzBay’s 75-day timeline?

Any office under 10,000 sq ft. ByzBay designs and builds it in 75 days at a fixed price agreed before work starts, planned as 15 days of design, 50 of build and 10 of snagging and move-in. Under ByzBay’s terms, the 75 days run from the day both sides sign off the final design and the site is handed over, and extend for changes you ask for, permits and approvals outside ByzBay’s control, and force majeure. A larger office falls outside that offer, so check your floor area first and do not assume the same programme.

What does a fixed price mean in practice?

The total is agreed before work starts, against a signed drawing and specification, so you know the number going in. If you change the scope later, the change is priced and agreed in writing first, and the fixed price keeps its meaning instead of drifting through the build.

Can the timeline shrink further?

Not safely. Each phase depends on the one before: the design must be frozen before the build, and snagging must follow completion. Compressing them usually creates rework. The practical way to protect the date is to make decisions fast in the first 15 days and order long-lead items early.

Is snagging really needed for ten days?

Yes, because it is where small defects are found and fixed before the team moves in. A scheduled snagging phase is cheaper than discovering problems after occupation. It also leaves time to test power, data and air conditioning at every desk with the final furniture in place.

What if my team grows during the project?

Raise it during the first 15 days, when the layout can still change at low cost. Add a growth allowance to the brief, such as extra desk positions with power and data already provided. Changes after the design freeze affect both the programme and the price.